Typical Projects of Dong Nam Company (Donatech 2019)

Dong Nam Technology Trading Joint Stock Company would like to send to our customers 2019
The entire Board of Directors and staff of our company would like to thank our customers during the past time, have been and will support using our services. With the satisfaction of our customers is our joy and success. In 2019 we have put our whole heart to complete the ''Supply thiết bị phòng cháy, thiết bị chữa cháy, construction of fire fighting system and fire alarm system'' effectively, quickly and on time for many fastidious customers nationwide.
With a team of enthusiastic and creative employees, we always complete the work of supplying equipment to partners, executing large and small projects throughout the year. With the timely encouragement of the Company's Board of Directors and the support from customers, we always accompany us during the construction of projects at the construction site.
The business motto and service provision of our Company in 2019 and the following year 2020 and the following years:
- Provide genuine products.
- Best price in the market.
- Fastest delivery, on time.
- Ensure construction on schedule according to economic contracts.
- The best service attitude.
2019 is a challenging year and also the pride of the entire Board of Directors, staff, employees, engineers.. who have completed the construction volume of the most prominent key projects.
1/ TMA SOFTWARE CENTER
Item of construction: Supply of materials, construction of fire alarm system, fire fighting system, lightning protection system.
Construction location: Ghenh Rang Ward, Quy Nhon City, Binh Dinh Province
Construction period: 20 months with 03 phases until the end of 2020 (Starting from 03/2019)
Contract value :5,130,000,000 VND
TMA Software Center – Ghenh Rang, Quy Nhon, Binh Dinh
2/ Le Tuyen Hoc Mon Co., Ltd
Implementation items: Supply of materials and construction of fire protection systems, lightning protection systems.
Construction location: 139 Le Loi, Hoc Mon, HCMC
Construction period: May 2019
Deadline and handover November 2019
Contract value: 1,900,000,000
Le Tuyen - Hoc Mon Co., Ltd
3/ ACB Bank Luy Ban Bich branch – Tan Phu
Implementation items: Design and construction of fire protection systems, fire alarm systems, lightning protection systems.
Construction location: 835-837 Luy Ban Bich, Tan Phu District, HCMC
Construction period: February 2019
Closing time and handing over December 2019
Contract value : 2,600,000,000
Asia Commercial Bank ACB – 835,837 Luy Ban Bich, Tan Phu
4/ Housing Office Luy Ban Bich - Tan Phu
Implementation items: Design and construction of fire protection systems, fire alarm systems, lightning protection systems.
Construction location: 595 Luy Ban Bich, Tan Phu District, HCMC
Construction period: October 2019
End time and handover in May 2020
Contract value : 2,400,000,000
Office building combined with 595 Luy Ban Bich
5/ 220KV . Substation
Implementation items: Supply of equipment, construction of fire protection systems, fire alarm systems.
Construction location: Phu Tai Intersection, Quy Nhon Binh Dinh
Construction period: January 2019
Closing time and handing over December 2019
Contract value : 1,640,000,000
220KV substation – Phu Tai, Quy Nhon, Binh Dinh
In addition to the above large and small projects, our company Dong Nam also provides many fire prevention and fighting equipment for many other construction units nationwide. All information Customers need to find out about information, technical advice, all issues related to the field of fire protection. Please contact us via our hotline: 0917.911.114 to get all your questions answered.